Motorways agency says will look again at costly and lengthy D1 modernisation

 
photo:  (radio.cz)
 

Drivers can be almost guaranteed a bumpy ride and delays on the country’s busiest stretch of motorway between Prague and Brno. Much of motorway is already in a poor state and modernization work on a few selected stretches have caused long queues. Now a debate has reopened over whether the Road and Motorway Agency is going about the reconstruction in the right way.

 

The D1 motorway is the Czech Republic’s main artery stretching from Prague to the second city Brno and then onwards to Ostrava. But the oldest stretches of the road constructed in large part at the end of the 1960’s are now showing their age. Driving on the route is often so bumpy that it often gives the impression that your wheels are square.

A staged six year modernization was launched last year but work on some of the sections almost immediately sparked disagreements between the contractors and the state Road and Motorway Agency with completion of the work looking like it will be significantly delayed.

Long queues have developed, occasionally stretching for up to 30 kilometres, on some of the sections and these are not even on the most used parts of the motorway, such as near Prague and Brno where on average around 100,000 and 70,000 vehicles a day pass by.

The head of the highways agency Jan Kubiš this week broached the problem and said that a faster and cheaper method of carrying out the modernization will now be looked at. Instead of digging up the existing concrete surface and base only the surface would be removed and covered in asphalt. So-called fragmentation is a commonly used procedure across Europe.

One of the main backers of this approach are members of a so-called shadow highways agency created by Czech coach service business and billionaire Radim Jančura. A leading member of the shadow agency is Jiří Petrák, until recently the head of the Prague office of international engineering and construction company Mott Macdonald.

I asked Mr. Petrák what the main problem was with the way the agency has organized the work so far:

“The main problem is that conceptually the modernization is too costly and too long in its execution. These are the main problems that we criticize.”

How much more expensive is the process and how longer is it than it should be.

“The problem with the motorway is that the surface quality has deteriorated so much that it needs to be improved. Conceptually the Road and Motorway Directorate has picked a method which calls for the replacement of both surface layers which are around half a meter thick with a new concrete structure. We propose that it would be much better to adopt the usual way of strengthening by adding a new asphalt layer, which is the usual way of modernising and improving the surface quality of motorways. There is at least a 60 percent difference in the cost for the overlay and there is probably a similar saving in time, about 60 percent.”

People say that if you use this method then the surface will last 10 to 15 years and then more work again would be needed. Is that correct?

“Every surface goes through a process of deterioration. With a new concrete surface we should assume that in 25 to 30 years that surface will need to be replaced again or need to be overlaid. But with this overlay now, with the properly designed thick overlay, the top surface layer would just be replaced every 15 years. Certainly there is some cost, but it’s still a fraction of the cost and every 15 years we have a perfect new surface, which is relatively cheap. Or, every 30 years we replace the concrete structure. This method is much more economical.”

 
 
Author: Český rozhlas Radio Praha
 
Added: 24.06.2014
 
 
 

Related articles

 
Business
 
 

Czech company tax among the most...

The Czech Republic’s system of company tax is one of the most complicated in the EU, claims a study made...

 
 
Business
 
 

Czech unions seek to force employers...

Companies in the Czech Republic will have to accurately track their employees’ working hours. Otherwise...

 
 
Business
 
 

Major new residential and office...

A new residential and office quarter is set to go up in the Prague 10 district that will contain up to...

 
 
Business
 
 

Czech Republic facing serious...

In the last few decades the number of teenagers who opted to become skilled tradesmen and women has seen...

 
Most favourite

History of Czech fine art

What happened in the realm of fine art at the very beginning of the Czech…

Climate

The Czech Republic is a landlocked country located in moderate geographical…

The most significant current discoveries

During the last decade, Czech science has made many revolutionary discoveries…

Czech language

The Czech language belongs to the group of West Slavic languages. From another…